IMG_1919IMG_1910On this project, we were responsible for the installation of a 30 Ton air handler and all the associated duct work. We also installed a Type 1 Hood, two package units and several exhaust fans.The store has an open ceiling design, meaning our duct work is exposed. This store created some unique challenges for us. This project had such a aggressive schedule it required us to install the main supply air trunk  line before the interior slab was poured. We also had to install the 30 Ton Air handler, which was shipped in 4 sections on a mezzanine that was only a platform. The walls were later built around it to close it in. We were able to meet this schedule and overcome all the installation challenges of this project.